Al Wadiah Bridge

The purpose of the project

Rehabilitation of the destroyed Al Wadiah Bridge

The importance of the project

A car bridge linking the villages south of the canal with the villages north of it

Project location and area

The project is located south of Al-Wadiah Village on the main canal – 48 meters long and 6.5 meters wide

OWNER

Public Corporation for Land Reclamation - Upper Euphrates Basin Branch

PROJECT INCEPTION

2020-04-01

previous arrow
next arrow
ArrowArrow
Slider

The main sections of the project:

  1. Create temporary earthen dams
  2. Dewatering between dams
  3. Cracking concrete and drilling to connect the foundations
  4. Planting pointers and casting tie bases, pillars and crowns
  5. Casting the side footboard
  6. Replay the damaged cladding and isolate it
  7. Preparing pre-made prizes, transporting and installing them on
  8. site, and replacing a damaged permissible
  9. Casting connecting slabs
  10. Preparing, transporting and installing prefabricated footpaths
    Fully insulate the bridge and install and insulate spacers
  11. Casting veneer slabs and installing metal drapery with paint