1- Establishing temporary dams
2- Dewatering between dams
3- Dismantling and storing valid piers / number 5 /
4- Concrete breaking and drilling to reach the foundations
5- Planting points and casting bases, columns and connecting crowns
6- Casting the side support.
7- Re-cast and isolate the damaged cladding
8- Preparing the pre-casted piers, transporting and installing them on site / number 10 / together with the valid piers.
9- Casting connecting slabs
10- Preparing, transporting and installing prefabricated footpaths.
11- Completely isolating the bridge and installing and isolating spacers
12- Casting veneer slabs and installing metal handrails with paint.